Dawson ISD Bond Update - July 9th, 2025
We are excited to share the latest updates on our bond project, focusing on the construction progress of the new football field:
Football Stadium
• Turf area gravel grading has been completed.
• Sidewalks around the track are receiving lime conditioning.
• Visitor and grandstand bleacher base materials are being installed.
• The visitor side bleacher foundation pour is underway.
• New road grading is currently in progress.
Field House and Concession Stand
• Concrete masonry unit interior wall installation is ongoing.
• Interior metal framed walls have been installed.
• One-sided sheet rock installation is currently underway.
• Mechanical, electrical, and plumbing rough-ins are progressing.
• Exterior brick veneer installation is also ongoing.